The Cory Cogeneration Station experienced a phase to ground fault on a 138 kV transformer termination.  The 138 kV cable traveling underground from the GSU transformer to the gas insulated switchgear in the 138 kV E-house was also damaged. 

Dynamo was retained to perform all required engineering and design requirements to meet all utility needs including plans review, grounding and bonding design, cable routing, and cable capacities.

Dynamo was retained to perform all required engineering and design requirements to meet all utility needs including plans review, grounding and bonding design, cable routing and cable capacities.

The primary objective of the Utility Power Upgrade Project was to install two (2) three-winding 230 kV power transformers to carry the site load and allow de-energization of the existing 72–4.16 kV substation.

The primary objective of the Utility Power Upgrade Project was to install two (2) three-winding 138 kV power transformers to carry the site load and allow de-energization of the existing 72–4.16 kV substation.