PROJECT SUMMARY
Hoist drive upgrades at the Nutrien Allan Potash Mine had caused undesirable harmonic effects that resulted in vibration and damage to the existing production hoist transformers, eventually leading to failure...
PROJECT SUMMARY
SECTOR:
Food
CLIENT:
Thunder Creek Pork
DURATION OF PROJECT:
3 Months
PROJECT SUMMARY:
Dynamo was retained to design a new controls interface for the main burner system at the Thunder Creek Pork facility in Moose Jaw, Saskatchewan. A combination of existing and new equipment was used to complete the design.
Dynamo performed the work on-site during a planned shutdown. Some existing cables were re-purposed, but the majority were replaced with new cables and heat shields.
Dynamo successfully commissioned the upgrade and assisted the client with process start-up.
Recent Posts
Hoist drive upgrades at the Nutrien Allan Potash Mine had caused undesirable harmonic effects that resulted in vibration and damage to the existing production hoist transformers, eventually leading to failure...
Dynamo executed the electrical and civil work for the brownfield 72 kV station at the QE6 (Q3N) In-Line Breaker Substation located near Saskatoon, SK...
Dynamo was contracted to fabricate, ship, and install a
16 m x 7.3 m switchgear building for the Parkridge Station in Regina, SK. The project was guided by a complete set of sealed drawings developed by Dynamo based on preliminary designs from SaskPower..