PROJECT SUMMARY
Hoist drive upgrades at the Nutrien Allan Potash Mine had caused undesirable harmonic effects that resulted in vibration and damage to the existing production hoist transformers, eventually leading to failure...
PROJECT SUMMARY
SECTOR:
Mining
CLIENT:
HudBay Minerals
DURATION OF PROJECT:
3 Weeks
PROJECT SUMMARY:
Hudbay Minerals is a diversified Canadian mining company producing copper concentrate and zinc metal in its operating facilities located in Manitoba and Peru. It owns and operates three polymetallic mines, four ore concentrators and a zinc production facility.
Dynamo was awarded the opportunity to supply a 20’ sea container E-House to HudBay Minerals in Snow Lake, Manitoba.
The exterior of the container was painted using site-specific paint standards and the interior was framed with 2 x 3 spruce studs, insulated with 2 lb closed cell spray foam, and finished with fire-resistant paint over sanded plywood sheeting.
Recent Posts
Hoist drive upgrades at the Nutrien Allan Potash Mine had caused undesirable harmonic effects that resulted in vibration and damage to the existing production hoist transformers, eventually leading to failure...
Dynamo executed the electrical and civil work for the brownfield 72 kV station at the QE6 (Q3N) In-Line Breaker Substation located near Saskatoon, SK...
Dynamo was contracted to fabricate, ship, and install a
16 m x 7.3 m switchgear building for the Parkridge Station in Regina, SK. The project was guided by a complete set of sealed drawings developed by Dynamo based on preliminary designs from SaskPower..