PROJECT SUMMARY

MLTC BioEnergy Panel Fabrication

  • 2.jpg
  • 1.jpg
  • Pic 2.jpg
  • IMG_E6086.jpg
  • Pic 1.jpg
  • 3.jpg
  • 4.jpg


SECTOR: 
Renewables


CLIENT: 

MLTC BioEnergy


DURATION OF PROJECT:

4 Months


PROJECT SUMMARY:


The MLTC BioEnergy facility is a carbon-neutral generating facility located at the Meadow Lake NorSask Sawmill site. The system is fueled by sawmill biomass residuals to generate roughly 6.6 MWs of green power.


Dynamo was contracted to fabricate a substation protection and control panel, three (3) PLC control panels, four (4) network cabinets, and an E-Stop panel. The client drawing package was closely reviewed and sorted to provide construction efficiencies as major supply chain issues were inevitable due to the effects of the global pandemic. Alternative products and solutions identified and proposed by Dynamo were quickly accepted by the client to avoid possible project delays.


Numerous design and wiring changes, along with device substitutions, were managed with close client and contractor communications resulting in a finished product being delivered on time and on budget despite unprecedented challenges presented to our project team schedule.

Recent Posts

Dynamo was retained to complete the decommissioning and disposal of one (1) 20 MVA transformer, BU-410-TX-1 and one (1) high voltage oil circuit breaker, BU-410-TX-1-OCB at the Bethune Station and one (1) 20 MVA transformer, ZP-420-TX-2 at the Loreburn Station.