PROJECT SUMMARY
Dynamo designed a greenfield substation and medium voltage distribution for a canola processing facility near Yorkton, SK.
PROJECT SUMMARY
SECTOR:
Mining
CLIENT:
Pentec Energy
DURATION OF PROJECT:
8 Months
PROJECT SUMMARY:
Nutrien is a Canadian fertilizer company headquartered in Saskatoon, Saskatchewan. It is the largest producer of potash and the third-largest producer of nitrogen fertilizer in the world. Nutrien produces and distributes over 25 million tonnes of potash, nitrogen and phosphate products for agricultural, industrial and feed customers worldwide.
Dynamo completed the installation and commissioning of the Brine Pond Expansion Pump House electrical system. The scope consisted of the installation and commissioning of 25 kV and 5 kV cables, a 25–5 kV oil-filled transformer, 5 kV switchgear and associated pumps, 600 V cabling, switchgear and associated 600 V loads, as well as 208 V distribution, cable terminations, and cable testing.
The project scope also included fibre optic services with approximately one hundred (100) terminations for the fire panel, motor relays, and switchgear connections, as well as one hundred (100) splices connecting underground fibre optic cables.
Recent Posts
Dynamo designed a greenfield substation and medium voltage distribution for a canola processing facility near Yorkton, SK.
Dynamo was retained to complete the decommissioning and disposal of one (1) 20 MVA transformer, BU-410-TX-1 and one (1) high voltage oil circuit breaker, BU-410-TX-1-OCB at the Bethune Station and one (1) 20 MVA transformer, ZP-420-TX-2 at the Loreburn Station.
Dynamo was retained to fabricate, ship, and install a 9.6 m x 4.5 m control building for the Grenfell Substation. Drawings were supplied by Dynamo based on a preliminary design provided by SaskPower.