PROJECT SUMMARY

Grenfell Substation – Supply of Control Building

  • ehouse2.jpg
  • ehouse.jpg
  • ehouse3.jpg


SECTOR: 
Agriculture


CLIENT: 

SaskPower


DURATION OF PROJECT:

6 Months


PROJECT SUMMARY:

Dynamo was retained to fabricate, ship, and install a 9.6 m x 4.5 m control building for the Grenfell Substation.  Drawings were supplied by Dynamo based on a preliminary design provided by SaskPower.


The building construction consisted of a steel skid and I-beam frame with a purlin and girt skeleton. The outside was covered with metal cladding and then finished inside with insulation, vapour barrier, interior walls, and plywood sheeting before being covered with a flat steel liner. Electrical, mechanical, washroom facilities, and raised access floor systems were installed.  Regular QA/QC visits from SaskPower were scheduled.


The scope of work also included shipping to site, placement and welding on the foundations, stair and septic tank installation, and commissioning of building systems.


Similar scopes of work and the same building designs were completed for the Hawarden, Paradise Hill, Riverhurst, Spruce Lake, and Turnor Lake substations.

Recent Posts

Hoist drive upgrades at the Nutrien Allan Potash Mine had caused undesirable harmonic effects that resulted in vibration and damage to the existing production hoist transformers, eventually leading to failure...

Dynamo executed the electrical and civil work for the brownfield 72 kV station at the QE6 (Q3N) In-Line Breaker Substation located near Saskatoon, SK...

Dynamo was contracted to fabricate, ship, and install a
16 m x 7.3 m switchgear building for the Parkridge Station in Regina, SK. The project was guided by a complete set of sealed drawings developed by Dynamo based on preliminary designs from SaskPower..