PROJECT SUMMARY
Hoist drive upgrades at the Nutrien Allan Potash Mine had caused undesirable harmonic effects that resulted in vibration and damage to the existing production hoist transformers, eventually leading to failure...
PROJECT SUMMARY
SECTOR:
Renewables
CLIENT:
MLTC BioEnergy
DURATION OF PROJECT:
4 Months
PROJECT SUMMARY:
The MLTC BioEnergy facility is a carbon-neutral generating facility located at the Meadow Lake NorSask Sawmill site. The system is fueled by sawmill biomass residuals to generate roughly 6.6 MWs of green power.
Dynamo was contracted to fabricate a substation protection and control panel, three (3) PLC control panels, four (4) network cabinets, and an E-Stop panel. The client drawing package was closely reviewed and sorted to provide construction efficiencies as major supply chain issues were inevitable due to the effects of the global pandemic. Alternative products and solutions identified and proposed by Dynamo were quickly accepted by the client to avoid possible project delays.
Numerous design and wiring changes, along with device substitutions, were managed with close client and contractor communications resulting in a finished product being delivered on time and on budget despite unprecedented challenges presented to our project team schedule.
Recent Posts
Hoist drive upgrades at the Nutrien Allan Potash Mine had caused undesirable harmonic effects that resulted in vibration and damage to the existing production hoist transformers, eventually leading to failure...
Dynamo executed the electrical and civil work for the brownfield 72 kV station at the QE6 (Q3N) In-Line Breaker Substation located near Saskatoon, SK...
Dynamo was contracted to fabricate, ship, and install a
16 m x 7.3 m switchgear building for the Parkridge Station in Regina, SK. The project was guided by a complete set of sealed drawings developed by Dynamo based on preliminary designs from SaskPower..