PROJECT SUMMARY

T5 Transformer Refurbishment

  • IMG_0493.jpg
  • IMG_0529.jpg
  • T5 Tank inspection (5) 1.jpg
  • T5 Tank inspection (11) 1.jpg


SECTOR:

Chemical


CLIENT: 

Chemtrade Logistics Inc.


DURATION OF PROJECT:

10 Days


PROJECT SUMMARY:


The T5 rectifier transformer at the Chemtrade Logistics’ plant in Brandon, MB had developed several moderate leaks over its service life resulting in an increased risk to the asset as well as potential environmental concerns.


Dynamo’s scope of work included the separation of the transformer from the rectifier, along with removal of all mineral oil, and re-gasketing of all flanged connection points including cooling radiators, inspection covers, and oil piping. An internal inspection was also completed at this time. The transformer was then re-installed and re-connected to the rectifier. The transformer was placed under vacuum and dried prior to filling with hot, filtered oil through Dynamo’s mobile oil processing unit. Once the transformer was filled, the oil was circulated to further condition the oil and transformer windings. A full set of electrical tests were then completed, and the transformer was back online within eight (8) days.

Recent Posts

The T5 rectifier transformer at the Chemtrade Logistics’ plant in Brandon, MB had developed several moderate leaks over its service life resulting in an increased risk to the asset as well as potential environmental concerns.

The University of Saskatchewan Preston Substation Upgrade Project consisted of upgrading all site equipment to migrate the facility from the current 72 kV primary voltage to 138 kV...

The scope of work consisted of the design, fabrication, and supply of a 24.6 m x 7.3 m prefabricated walk in E-House installed at the Mosaic Potash Belle Plaine mine site...